2021 Study Schedule – The following studies will be undertaken and start dates are tentative:
- April – Tributary Access Survey
- May through June- Wood Turtle Study
- July through August – Study components of Recreation, Magalloway Temp, Magalloway Mesohabitat, Aquatic Habitat, Benthic Macroinvertebrate, Impoundment Trophic State
- September through October – Cultural surveys
Process Plan – The process plan includes the schedule and dates for the entire relicensing process. This plan is subject to FERC’s review and approval.